Downloads
Shisane Reinforcing provides total reinforcing solutions, including:
Labour Allocation Calculators
| Labour allocation calculator (conventional structures) |
| Example: |
Enter your own values below to calculate your
required labour allocation for conventional structures: |
 |
|
Formula:
20 ton ÷ 4 days = 5 ton
5 ton х 35 manhours per ton = 175 manhours
175 manhours ÷ 8 working
hours per day = 22 fixers |
| Labour allocation calculator (post-tensioning structures) |
| Example: |
Enter your own values below to calculate your
required labour allocation for conventional structures: |
 |
|
Formula:
20 ton ÷ 4 days = 5 ton
5 ton х 40 manhours per ton = 200 manhours
200 manhours ÷ 8 working
hours per day = 25 fixers |
Calculating estimated tonnage without available drawings and bending schedules |
Example:
(Calculate cubic metres) |
Enter your own values below to calculate your
required labour allocation for conventional structures: |
 |
|
Formula:
L x W x H
Example of a slab of 30m x 12m x 255mm
Calculation 30 x 12 x .255 = 91.8m3
91.8m³ x 80kg /m³ = 7.344 ton of reinforcing |
|